📋 Project Overview

Goal: Design and develop a working prototype using C programming concepts learned throughout the semester including variables, loops, functions, arrays, structures, and file handling.

Working Mode: Individual

💻 Working Code

Must compile and run without errors. Should be menu-driven with proper functionality.

20 Marks

📄 Project Report

Comprehensive documentation following the prescribed format (6-10 pages).

10 Marks

🎯 Total Marks

Combined evaluation of code implementation and documentation quality.

30 Marks

💡 Project Topics Examples

Note: You are not limited to these topics! Feel free to choose any topic or idea that interests you and aligns with C programming concepts. The examples below are provided as inspiration to help you get started. You can work on your own creative project idea as long as it demonstrates the required programming concepts.

BASIC LEVEL Console Programs

Sr. No Project Title Concepts Used
1 Student Result Management System Arrays, functions, conditional statements
2 Library Book Record System File handling, struct, search
3 Online Quiz Test Loops, functions, switch case
4 Billing System for Grocery Store Structures, arrays, loops
5 Railway Ticket Reservation (Simplified) Arrays, conditional statements

INTERMEDIATE LEVEL File Handling + Structures

Sr. No Project Title Concepts Used
6 Contact Management System File handling, CRUD operations
7 Hostel Room Allocation System Structures, functions
8 Bank Account Management Functions, file I/O
9 Inventory Management System Struct + file + search
10 Attendance Tracking System File + menu driven program
📌 Important: Choose one project based on your interest and skill level. Intermediate projects offer more complexity and learning opportunities.

📝 Project Report Format

📥 Download Template:

📄 C Programming Project Report Template.docx

Click to download the template and prepare your report accordingly.

Page Limit: 6-10 pages

  1. Title Page - Project title, student name, roll number, semester
  2. Problem Statement - Clear description of the problem being solved
  3. Objective of the Project - Goals and expected outcomes
  4. Software Used - Compiler, IDE, operating system
  5. Algorithm - Step-by-step logical approach
  6. Flowchart / Pseudocode - Visual representation of program flow
  7. Screenshots of Output - Multiple test cases with results
  8. Source Code - Complete C program with comments
  9. Conclusion & Future Enhancement - Learning outcomes and improvement scope

📊 Evaluation Rubric

Code Evaluation (20 Marks)

Criterion Marks
Compilation & Execution 5
Correct Output 5
Code Quality (modularity, comments, functions) 5
Creativity & Additional Features 5
Total 20

Report Evaluation (10 Marks)

Criterion Marks
Presentation (formatting, structure) 3
Algorithm & Flowchart 3
Code Documentation inside Report 2
Conclusion & Future Scope 2
Total 10

📅 Project Timeline

Follow the timeline below to stay on track with your project milestones and ensure timely completion.

Project Timeline

✅ Submission Guidelines

  • Submit working C source code (.c file)
  • Submit project report in PDF format as well as hard copy.
  • Ensure code compiles without errors
  • Include proper comments in code
  • Test program with multiple test cases
  • Follow naming convention: RollNumber_ProjectName.c